June 7th, 2008. The Ceremony of Opening of the Construction Site marking by the putting of the 1st stone in bed of the Bridge across the strait between the mainland and the Koh Puos Island by the City of Sihanukville. >>
April, 2008. The official permit for the bridgework construction for KPIG was received from the Ministry of Public Works and Transport of Cambodia.
March, 2008. The KPIG obtained the approval of its project design from the Ministry of Public Works and Transport of Cambodia.
February, 2008. KPIG started Conceptual Design Works on Koh Puos Island and related area.
November, 2007. The contract for the bridge work was signed between KPIG and Sinohydro Corporation Ltd.
October, 2007. The Council for the Development of Cambodia issued the Letter to Transfer- Receive a leased site of Koh Puos Island and Hawaii Beach, Sihanoukville.
October, 2007. The Inter-ministerial Commission of the Council for the Development of Cambodia jointly approved Master Plan and Development Schedule.
August, 2007. The Land Lease agreement for the place on the mainland for connection with Koh Puos Island was signed.
August, 2007. KPIG received the Approval of Bridge Main Technical Specifications.
July, 2007. The Development Schedule of Koh Puos Project realization was filed for approval of Council for the Development of Cambodia.
June, 2007. The Master Plan of Koh Puos Project was filed for CDC approval.
May-July 2007. The Investigations for the Bridge works location were fulfilled.
February - April, 2007. The Survey Investigations and Exploratory Works on Koh Puos Island were executed.
December, 2006. Mr. Alexander Kiryushin was appointed the Chairman of the Board. Mr. Yury Alekseenko was appointed the Director of KPIG.
September, 2006. The Lease Agreement of Koh Puos, Sihanoukville was signed between the Royal Government of the Kingdom of Cambodia and KPIG.
August, 2006. The Koh Puos (Cambodia) Investment Group Ltd (KPIG) received The Registration Certificate.
|